Project Name:

Project Manager:

Date:

Task ID Task Name Start Date End Date Duration Owner Status Dependencies
1 Project Kickoff [MM/DD] [MM/DD] X days [Name] Not Started/In Progress/Completed -
2 Requirements Gathering [MM/DD] [MM/DD] X days [Name] Not Started/In Progress/Completed Task 1
3 Design / Planning [MM/DD] [MM/DD] X days [Name] Not Started/In Progress/Completed Task 2
4 Implementation [MM/DD] [MM/DD] X days [Name] Not Started/In Progress/Completed Task 3
5 Testing / QA [MM/DD] [MM/DD] X days [Name] Not Started/In Progress/Completed Task 4
6 Deployment / Launch [MM/DD] [MM/DD] X days [Name] Not Started/In Progress/Completed Task 5
7 Project Close / Lessons Learned [MM/DD] [MM/DD] X days [Name] Not Started/In Progress/Completed Task 6